13. The voltage value should be measured before the replacement of the new module.
The voltage value should be consistent with the voltage value of the adjacent
module. The voltage value should be adjusted by the charging and discharging
equipment,Differential pressure is ±10mv
13.在换上新模组之前,要测量新模组电压,电压值要与相邻模组电压值一致,
电压值使用充放电设备调整,压差在±10mv。
14. After replacing the module, remember to apply conductive paste between
adjacent modules, reassemble the module, and lift the module back into the
battery pack with tooling
14.更换完模组后,记得涂抹相邻模组间的导电膏,将模组重新组装好,并用工
装将模组抬回电池包内。
Note:
注意事项:
1 When pulling out LBC low-voltage harness, pull it out from high-end to
low-end
1 拔出 LBC 低压线束时,从高端到低端拔出
2 The cooling pipe belongs to the loss part, and its service life is inserted
and unplugged three times. After three times, it is recommended to replace the
cooling pipe with a new one after unpacking
2 冷却管路属于损耗件,使用寿命插拔 3 次,后续拆包建议更换新的冷
却管路。
3 After removing the cooling pipe, use adhesive tape or other tools to
block the cooling pipe interface of the module to prevent foreign matter from
entering
3 在拆下冷却管路后,要用胶布或者其他工具封堵模组的冷却管路接口,
防止异物进入
4 When lifting the module back into the battery pack, be careful not to
damage the cooling pipe under the metal bracket
4 将模组抬回电池包内时,注意金属支架不要损坏下方的冷却管路
5 Disconnect the high-voltage soft connection, must be insulated